Basis for Implementation of the Project:

  • Directive of the Russian Government No. 635-r dated 22 April 2010 On design and Construction of the Zapolyarye – Purpe – Samotlor Oil Trunk Pipeline, as amended in directives of the Russian Government No. 1884-r dated 28 October 2010, No. 2068-r dated 18 November 2011 and No. 2345-r dated 24 November 2014.

The Goal of the Project:

Enabling intake of crude from new oilfields in Yamal-Nenets Autonomous Area into the system of oil trunk pipelines.

Within the implementation of the project, an oil trunk pipeline with the throughput capacity of 32 MTPA was constructed (with potential to increase its throughput capacity to 45 MTPA), which includes line facilities; new oil pumping stations were constructed, and the existing oil pumping stations with tank farms were expanded; external power supply facilities, operational and infrastructure facilities were constructed.

The project was delivered in 2016.