Scroll to top

Construction of Volgograd Refinery PPTP – Tinguta MPS section

Project implementation basis:

  • Agreement No.1410281 dated 30 May 2014 on cooperation of Transneft and LUKOIL in the implementation of joint projects;
  • Contract No.201500098-03-92/2015 dated 26 January 2015 for connection of LUKOIL-Volgogradneftepererabotka Oil Refinery to Kuybyshev-Tikhoretsk trunk oil pipeline and Volgograd-Tikhoretsk trunk petroleum products pipeline.

Project implementation objective:

Provide an intake of 4 MTPA of EURO-5 class diesel fuel produced by LUKOIL-Volgogradneftepererabotka to Transneft PPTP system.

The project includes construction of a pump station at Volgograd Refinery and a 4 MTPA trunk oil pipeline section to PPTP Volgograd-Tikhoretsk.

The project completion is scheduled in 2017.